Projects / References
AbbVie Operations Singapore Pte Ltd, Singapore – Site Improvement Projects

    Site Improvement Projects, (Water for Injection Generation / Storage and Distribution       
    System Installation; Clean Steam Generation and Distribution System Installation,
    Media Prep / Buffer Prep / Buffer Hold Vessel and Associated Piping Installation). -
    Responsible for 3D process & utility piping design, as well as, process skid design,
    vendor and design firm coordination.  Design activities on project included: 3D process
    equipment and piping model development with material database, equipment platform
    design, piping plan and detail development, piping fabrication isometrics, facility
    equipment layout, piping material and installation specifications, design checking,
    vendor submittal review, model design reviews via internet.

Lonza Biologics, Portsmouth, NH – NG3M Project

    Mid-Scale Cell Culture Facility. - Responsible for 3D process piping design, process
    and process utility module design and coordination. Supervised Designers.  Design
    activities on project included: BIM / MEP coordination, 3D process piping model
    development with material database, facility equipment layout, piping material and
    installation specifications, design checking, vendor submittal review, process
    equipment / module vendor coordination and construction support.

Micron Memory, Hiroshima Japan – Fab 15 Project (through M+W Group)

    Fab 15 Project. - Responsible for 3D space coordination and equipment/tool installation
    plans. Design activities on project included: 3D equipment/tool and piping model
    development, facility equipment/tool layout, design checking, vendor submittal review,
    3D model design reviews and construction installation support.

AbbVie Operations Singapore Pte Ltd, Singapore – Site Improvement Projects

    Site Improvement Projects, (Water for Injection Distribution Modifications, CIP Skid
    Installation, Caustic Dilution Skid Installation, Final Product Vessel Installation). -
    Responsible for 3D process & utility piping design, as well as, skid vendor coordination,
    equipment installation plans. Design activities on project included: 3D process
    equipment and piping model development with material database, piping plan and
    detail development, piping fabrication isometrics, facility equipment layout, piping
    material and installation specifications, design checking, vendor submittal review,
    model design reviews via internet..

Lonza Biologics Tuas Pte Ltd, Singapore – Water for Injection Distribution Expansion

    Water for Injection Distribution Expansion. - Responsible for 3D equipment and process
    piping design for WFI loop (700 meters long with 35 use points). Design activities on
    project included: 3D process equipment and piping model development with material
    database, piping plan and detail development, piping fabrication isometrics, facility
    equipment layout, piping material and installation specifications, design checking,
    vendor submittal review, model design reviews via internet.

Kenyon Pte Ltd, Singapore – Novartis DSP and Xolair Projects

    Downstream Purification Module & COP/SOP Station. - Responsible for 3D process
    module design and coordination. Supervised Designers.  Design activities on project
    included: P&ID development support, facility equipment layouts, 3D model development
    of skid framework, equipment, piping, control panels, conduit/cable tray, instruments;
    frame fabrication drawings, piping fabrication isometrics, piping material and
    installation specifications, design checking, vendor submittal review, vendor fabrication
    support, and construction installation support.

Novartis Singapore Pharmaceuticals Manufacturing Pte Ltd, Singapore – SGBO 2 Project

    Large Scale Cell Culture Facility. - Responsible for 3D process piping design, process
    and process utility module design and coordination. Supervised Designers.  Design
    activities on project included: BIM / MEP coordination, 3D process piping model
    development with material database, piping plan and detail development, piping
    fabrication isometrics, facility equipment layout, piping material and installation
    specifications, design checking, vendor submittal review, process equipment / module
    vendor coordination and construction support.

Roche Diagnostics (Suzhou) Ltd, Suzhou, China – IVD Greenfield Project

    Purified Water Compounding Station and COP/SOP Station Design. - Responsible for
    design of (11) fixed and mobile compounding stations and (3) COP/SOP stations.  
    Design activities on project included: P&ID development support, facility equipment
    layouts, 3D model development of skid framework, equipment, piping, control panels,
    conduit/cable tray, instruments; frame fabrication drawings, piping fabrication
    isometrics, piping material and installation specifications, design checking, vendor
    submittal review, and vendor fabrication support.

Novartis Singapore Pharmaceuticals Manufacturing Pte Ltd, Singapore – BioPharmOps
Project (through Jacobs Engineering)

    Large Scale Cell Culture Facility, Grass Roots. - Responsible for 3D process piping
    design, upstream manufacturing process module design and coordination. Supervised
    (10) Designers.  Design activities on project included: BIM / MEP coordination, 3D
    process piping model development with material database, piping plan and detail
    development, piping fabrication isometrics, facility equipment layout, piping material
    and installation specifications, design checking, vendor submittal review, process
    equipment / module vendor coordination and construction support.

Roche Singapore Technical Operations Pte Ltd, Singapore – DI/WFI Water Upgrade Project

    Deionized Water/Water For Injection Generation and distribution Expansion. -
    Responsible for new 3D process piping design and existing piping design
    modifications. Design activities on project included: BIM / MEP coordination, 3D process
    piping model development with material database, piping plan and detail development,
    piping fabrication isometrics, piping material and installation specifications, design
    checking, vendor submittal review, and construction support.

Lonza Biologics Tuas Pte Ltd, Singapore – Media Prep Suite Addition

    Media Prep Suite Addition. - Responsible for 3D suite design of equipment, platform,
    vessels, process and utility piping design. Design activities on project included: BIM /
    MEP coordination, 3D process equipment and piping model development with material
    database, piping plan and detail development, piping fabrication isometrics, facility
    equipment layout, piping material and installation specifications, design checking,
    vendor submittal review, model design reviews via internet.

Lonza Biologics, Portsmouth, NH – Purification Suite Build-out (through Parsons)

    Purification Suite Build-out, 2 story expansion. - Responsible for 3D model
    management of entire project, which included process skid and equipment vendors.  
    3D model management activities included: BIM / MEP coordination, development of
    project modeling guidelines, discipline space coordination and clash resolutions, 3D
    model reviews via internet. Design activities on project included: 3D process equipment
    and piping model development with material database, piping plan and detail
    development, piping fabrication isometrics, process equipment vendor coordination,
    facility equipment layout, piping material and installation specifications, design
    checking, vendor submittal review, and construction support.

Baxter Bioscience, Hayward, CA – Lab Relocation Project

    Lab Relocation Project. - Responsible for lab demolition drawing package, lab general
    arrangement plan, lab utility and piping design, and installation drawing package.

Roche Singapore Technical Operations Pte Ltd, Singapore – Clean Steam Distribution
Expansion (through Lifetek Solutions)

    Clean Steam Distribution Expansion. - Responsible for 3D process piping design
    modifications. Design activities on project included: BIM / MEP coordination, 3D process
    piping model development with material database, piping plan and detail development,
    piping fabrication isometrics, piping material and installation specifications, design
    checking, vendor submittal review, and construction support.

Lonza Biologics Tuas Pte Ltd, Singapore – Water for Injection Storage and Distribution
Expansion (through Lifetek Solutions)

    Water for Injection Storage and Distribution Expansion. - Responsible for 3D skid
    design of process piping design. Design activities on project included: BIM / MEP
    coordination, 3D process equipment and piping model development with material
    database, piping plan and detail development, piping fabrication isometrics, facility
    equipment layout, piping material and installation specifications, design checking,
    vendor submittal review, model design reviews via internet.

Lonza Biologics Tuas Pte Ltd, Singapore – Media Prep Tri-Blender Installation and Process
Piping Modifications

    Media Prep Tri-Blender Installation and Process Piping Modifications. - Responsible for
    3D design of process piping modifications. Design activities on project included: 3D
    process equipment and piping model development with material database, piping plan
    and detail development, piping fabrication isometrics, facility equipment layout, piping
    material and installation specifications, design checking, vendor submittal review,
    model design reviews via internet.

Novartis, Emeryville, CA – Laboratory Renovation (through Ipurity)

    Laboratory Renovation Project (Fully 3D modeled) - Responsible for BIM / MEP
    coordination, 3D process/mechanical piping design, including existing site utility survey
    information, piping plans and details.

Lonza Biologics Tuas Pte Ltd, Singapore – WFI Storage and Distribution Loop System Addition
(through Lifetek Solutions)

    WFI storage vessel, heat exchangers, distribution pumps and distribution loop addition
    for new building addition.  - Responsible for BIM / MEP coordination, 3D design of
    equipment skids and piping design. Design activities on project included: 3D process
    equipment and piping model development with material database, piping plan and
    detail development, piping fabrication isometrics, facility equipment layout, piping
    material and installation specifications, design checking, vendor submittal review,
    model design reviews via internet.

Bayer Healthcare, Berkeley, CA – Portable Vessel Blast Thaw Station (through Ipurity)

    Portable Vessel Blast Thaw Station - Responsible for 3D process/mechanical piping
    design, including existing site survey information, process/utility P&ID development,
    vessel configuration, space coordination, piping plans and details.

Novartis, Holly Springs, NC – Technology Development Pilot Plant (through Lifetek Solutions)

    New Pilot Plant Facility Project (Fully 3D modeled) - Responsible for 3D
    process/mechanical piping design, including existing site utility survey information,
    process/utility P&ID development, BIM / MEP coordination, piping plans and details.

Allergan, Waco, TX – Process/Compounding Skid (through DCI/Lifetek Solutions)

    Process/Compounding Skid w/ (3) process vessels, frame and supporting
    process/utility piping and accessories. - Responsible for 3D skid design. Design
    activities on project included: 3D process equipment, frame and piping model
    development, skid assembly plan and detail development, piping fabrication isometrics,
    piping material and installation specifications, design checking, vendor submittal
    review, and skid fabrication support.

Roche Singapore Technical Operations Pte Ltd, Singapore – WFI Loop & Storage
Modifications

    Piping and Control Modifications to WFI Return Loop and Storage Systems. -
    Responsible for 3D process piping design modifications. Design activities on project
    included: BIM / MEP coordination, 3D process equipment and piping model
    development with material database, piping plan and detail development, piping
    fabrication isometrics, facility equipment layout, piping material and installation
    specifications, design checking, vendor submittal review, and construction support.

Roche Singapore Technical Operations Pte Ltd, Singapore – Waste Water System Upgrade

    Waste Water System Modifications. - Responsible for 3D model management,
    equipment arrangements and piping design. 3D model management activities
    included: discipline space coordination and clash resolutions, 3D model reviews via
    Webex. Design activities on project included: 3D equipment and piping model
    development with material database, piping plan and detail development, equipment
    vendor coordination, facility equipment layout, piping material and installation
    specifications, design checking, vendor submittal review, and construction support.

Lonza BioSciences Singapore Pte Ltd, Singapore – Water Pre-Treatment Upgrade

    Piping modifications required for addition of (2) UV Sterilization Units. - Responsible for
    3D piping design modifications. Design activities on project included: 3D process
    equipment and piping model development with material database, piping plan and
    detail development, piping fabrication isometrics, facility equipment layout, piping
    material and installation specifications, design checking, vendor submittal review, and
    construction support.

Lonza BioSciences Singapore Pte Ltd, Singapore – Multiple Customer Filtration Modifications

    Piping modifications required for additional product filtration installations. - Responsible
    for 3D process piping design modifications. Design activities on project included: 3D
    process equipment and piping model development with material database, piping plan
    and detail development, piping fabrication isometrics, facility equipment layout, piping
    material and installation specifications, design checking, vendor submittal review, and
    construction support.

Lonza BioSciences Singapore Pte Ltd, Singapore – (2) 200L Bioreactor Installation

    Piping modifications required for installation of (2) 200L Bioreactors. - Responsible for
    3D process and utility piping design modifications. Design activities on project included:
    3D process equipment and piping model development with material database, piping
    plan and detail development, piping fabrication isometrics, facility equipment layout,
    piping material and installation specifications, design checking, vendor submittal
    review, and construction support.

Roche Singapore Technical Operations Pte Ltd, Singapore – Purified Water System

    Design and Installation of new Purified Water System including generation, storage and
    distribution. - Responsible for 3D model management, process equipment design and
    process piping. 3D model management activities included: BIM / MEP coordination,
    development of project modeling guidelines, discipline space coordination and clash
    resolutions, 3D model reviews via Webex. Design activities on project included: 3D
    process equipment and piping model development with material database, piping plan
    and detail development, piping fabrication isometrics, process module vendor
    coordination, facility equipment layout, piping material and installation specifications,
    design checking, vendor submittal review, and construction support.

Baxter Bioscience, Hayward, CA – Plant Steam Boiler Replacement

    Plant Steam Boiler Replacement along with Steam Distribution and Condensate Return
    Piping. - Responsible for demolition drawing package, boiler room general
    arrangement plan, 3D steam and condensate piping design, and installation drawing
    package. Also assisted with vendor submittal reviews and field construction support.

Dendreon, Seal Beach, CA – Immunotherapy Manufacturing Facility (through Lifetek Solutions)

    Immunotherapy Manufacturing Facility Project (Fully 3D modeled) - Responsible for 3D
    process/mechanical piping design, including piping plans and details. Assisted with
    field construction support.

Dendreon, Union City, GA – Immunotherapy Manufacturing Facility (through Lifetek Solutions)

    Immunotherapy Manufacturing Facility Project (Fully 3D modeled) - Responsible for 3D
    process/mechanical piping design, including piping plans and details.

Lonza Biologics Tuas Pte Ltd, Singapore – Large Scale Cell Culture Facility (through Parsons)

    Large Scale Cell Culture Project LBXS-2, 280,000 Sq. Ft. Grass Roots Facility (Fully 3D
    modeled). - Responsible for 3D model management of entire project, which included 2
    major Engineering Firms and 5 major Process Module/Super Skid vendors located in
    various global locations. 3D model management activities included: BIM / MEP
    coordination, development of project modeling guidelines, discipline space
    coordination and clash resolutions, 3D model reviews via Webex. Design activities on
    project included: 3D process equipment and piping model development with material
    database, piping plan and detail development, piping fabrication isometrics (1200+
    isos created), process module vendor coordination, facility equipment layout, piping
    material and installation specifications, design checking, vendor submittal review, and
    construction support.

BioMarin Pharmaceutical Inc., Novato, CA – Heat Treatment Skid (through Lifetek
Solutions/DCI)

    Heat Treatment Skid - 650L process vessel, heat exchanger, pump w/process and utility
    piping. Used for heating/cooling a process intermediate stream to remove background
    impurities. - Responsible for 3D skid design, including client model reviews via Webex,
    assembly drawing, frame details, and piping fabrication isometric drawings. Assisted
    with vendor submittal reviews, and shop fabrication support.

Roche (Lonza Biologics Singapore Pte Ltd), Singapore – Large Scale Cell Culture Facility
(through Parsons)

    Large Scale Cell Culture Project LBXS-1, 280,000 Sq. Ft. Grass Roots Facility (Fully 3D
    modeled). - Responsible for 3D model management of entire project, which included 2
    major Engineering Firms and 5 major Process Module/Super Skid vendors located in
    various global locations. 3D model management activities included: BIM / MEP
    coordination, development of project modeling guidelines, discipline space
    coordination and clash resolutions, 3D model reviews via Webex. Design activities on
    project included: 3D process equipment and piping model development with material
    database, piping plan and detail development, piping fabrication isometrics (1100+
    isos created), process module vendor coordination, facility equipment layout, piping
    material and installation specifications, design checking, vendor submittal review, and
    construction support. Less than 2% high purity piping re-work for piping designed by
    Axis Point Design.

Baxter Bioscience, Hayward, CA – 1600L & 400L Bioreactor Installation

    Modified existing Cell Culture Suite to install new 1600L & 400L Bioreactors. -
    Responsible for process/utility piping distribution modifications and design. Also
    responsible for contractor coordination, on behalf of Baxter, as well as updating utility
    system P&ID and piping drawings, HVAC air flow diagrams, HVAC pressurization and
    classification drawings maintained as Baxter Master Files.

Baxter Bioscience, Hayward, CA – CoSeal/FloSeal Relocation

    Relocated existing CoSeal/FloSeal manufacturing from Fremont, CA facility to Hayward,
    CA facility. - Responsible for process/utility system as-builts and HVAC system as-
    builts, updating process/utility system P&ID and piping drawings, HVAC air flow
    diagrams, HVAC pressurization and classification drawings.

Baxter Bioscience, Hayward, CA – Purification Suite Modifications

    Expanded existing Purification Suite into existing Cell Inoculum & Gowning Rooms. -
    Responsible for utility system modifications and HVAC modifications, updating utility
    system P&ID and piping drawings, HVAC air flow diagrams, HVAC pressurization and
    classification drawings.

Dey L.P., Napa, CA – Clinical Pilot Plant, Detailed Design (through IPS)

    Detailed design for 4,000 sq. ft. pilot plant for clinical and product launch quantities of
    products using Form/Fill Seal technology. - Responsible for equipment layouts, plant
    and process utility distribution p&ids, plant and process utility distribution piping,
    process waste and plumbing systems, piping system specifications.

Amgen, Bothell, WA – Wastewater Treatment System Replacement (through IPS)

    Replacement of 8,500 gallon neutralization tank, bulk acid and caustic storage tanks,
    metering pumps, and associated piping. - Responsible for project management,
    equipment specification, equipment arrangements, piping design and specification,
    vendor submittal review, construction management and commissioning.

Orthovita, Malvern, PA – Costasis/Vitagel Relocation (through IPS)

    Relocation of purchased product process from Palo Alto, CA to Malvern, PA. -
    Responsible for site utility survey, P&ID development, equipment specification, fixture
    detail design, facility layout, process and utility piping design, vendor submittal review,
    construction support.

Baxter Bioscience, Fremont, CA – Purified Water System As-Builts

    Required as-builts of Purified Water System P&ID and piping drawings. - Responsible
    for system walk down verification, updating system P&ID and piping drawings.

Baxter Bioscience, Hayward, CA – Process and Utility System As-Builts

    Required as-builts of Process and Utility System P&IDs, facility and piping drawings. -
    Responsible for system walk down verification, updating system P&IDs, updating facility
    drawings, updating piping drawings, CAD standard development, document control
    protocol.

Amgen, Bothell, WA – HVAC System As-Builts (through IPS)

    Required as-builts of cell culture facility HVAC system. - Responsible for system walk
    down verification, updating system P&IDs, updating facility HVAC drawings.

Lonza Biologics, Portsmouth, NH – Large Scale Build-Out Project (through Parsons)

    Large Scale Build-Out Project 280,000 Sq. Ft. Cell Culture Facility Expansion. -
    Responsible for piping design activities of intelligent P&ID development, 3D equipment
    and piping model development with material database for process modules, piping
    plan and detail development, piping fabrication isometrics, process module vendor
    coordination, facility equipment layout, plumbing plan development, piping material and
    installation specifications, design checking, vendor submittal review, and construction
    support.

References